Advent 1, 2 & 3 saw us appointed by Thomasons to support intensive fire-remediation works on three residential buildings in Ancoats, Manchester. Ranging between five and seven storeys and containing 386 apartments, the project involved removing noncompliant cladding and replacing it with a fully fire-safe façade system.
Project Credits
- ThomasonsClient
- ManchesterLocation
- Residential Sectors
- Retrofit, Architecture Services
- 386 apartmentsSize
- 2020 - 2024Programme
- CompleteStatus
3 buildings
remediated
Spanning
five to seven storeys
386 apartments
made safer
Supported by
the Building Safety Fund
The Brief & Design Development
We were commissioned to undertake an extensive review of the facade systems across the three buildings with respect to fire safety. Our work began with analysing the external wall build-ups, cladding and fire and cavity barriers. Through this process, we identified several non-compliant wall types requiring remediation. There were also specific attachments such as deck access walkways and facade interfaces with other building elements which also required remediation.
The complexity of the programme became clear as the variety of wall types emerged. Detailed external wall surveys revealed that metal and timber cladding systems and insulated render system all contained combustible elements that required immediate removal following legislative changes after the Grenfell tragedy. Each element demanded bespoke detailing and technical solutions.
Additional challenges were identified at key interface points. The interaction between the balconies and the building fabric required careful integration with cavity-barrier systems. The courtyard-facing façade also presented water-ingress issues, and services mounted externally on the building created further regulatory complications.
“With the projects subject to funding from the Government's Building Safety Fund (BSF), the team worked at speed to resolve complex technical solutions and drawings to ensure the project stayed on track to meet the funding deadlines.”David James Senior Architect, AEW Architects
The Outcome
Our final proposals saw the façade stripped back to the steel-frame system (SFS), with the timber cladding finish replaced with cement boards and the system components to both the timber and metal cladding replaced with non-combustible alternatives. The previous render system, which incorporated combustible external wall insulation, was substituted with a fully compliant, non-combustible alternative.
To resolve issues arising from the side-mounted services, we designed an enclosed system integrated into the façade using mesh panelling, allowing the services to blend neatly with the building’s appearance. Water-ingress concerns were eliminated through bespoke cladding detailing.
Working collaboratively with Thomasons, we have delivered a rejuvenated, fully compliant and fire-safe apartment complex. All combustible materials on the facade have been removed and replaced with robust, durable alternatives—ensuring safer homes and an enhanced building performance for residents.
The remediation works included the removal and replacement of:
- Non-compliant render systems and cladding systems including railings, insulation, cavity barriers and sheathing boards.
- Non-compliant timber decking to balconies and walkways.
- Non-compliant services enclosures to the underside of the deck access.